COMMISSION REGULATION (EC) No 271/2008
of 30 January 2008
amending Regulation (EC) No 794/2004 implementing Council Regulation (EC) No 659/1999 laying down detailed rules for the application of Article 93 of the EC Treaty
THE COMMISSION OF THE EUROPEAN COMMUNITIES,
Having regard to the Treaty establishing the European Community,
Having regard to Council Regulation (EC) No 659/1999 of 22 March 1999 laying down detailed rules for the application of Article 93 of the EC Treaty (1), and in particular Article 27 thereof,
After consulting the Advisory Committee on State Aid,
Whereas:
|
(1) |
In order to facilitate and accelerate the submission of State aid notifications by Member States, and their assessment by the Commission, it is desirable to generalise the use of the already established electronic systems. |
|
(2) |
Since 1 January 2006 Member States have been required to transmit State aid notifications electronically. The web application State Aid Notification Interactive (SANI) (2) has become fully functional and has increased the efficiency of procedures. For these reasons, from 1 July 2008, its use should be rendered obligatory for Member States for the submission of State aid notifications to the Commission. |
|
(3) |
Since 1 January 2006, Member States have also been required to transmit all correspondence in connection with notifications electronically. The secured e-mail system Public Key Infrastructure (PKI) (3) tested by the Commission has become fully functional. Its use should therefore be rendered obligatory, from 1 July 2008, for all correspondence from Member States to the Commission in connection with a notification. |
|
(4) |
In exceptional cases, upon the agreement of the Commission and the Member State concerned, it should be possible to use a communication channel other than the established web application or secured e-mail system. |
|
(5) |
Member States should be invited to submit a separate non-confidential version of the notification, on a voluntary basis, or any correspondence in connection with a notification where these documents contain confidential information. This should lead to shortening of procedures and should enable the Commission to decide more easily on requests for access to documents. The classification of the information as confidential should be justified by the Member State concerned. The submission of a separate non-confidential copy of the notification or any correspondence in connection with a notification is without prejudice to the assessment by the Commission of the confidential character of the information submitted. |
|
(6) |
In order to improve transparency of State aid in the Community, Member States should be required to refer to the State aid identification number allocated to the aid scheme concerned by the Commission in each grant of aid to a final beneficiary, save for aid granted through fiscal measures. For the same reason, the notification form should be modified to include an undertaking to publish on the Internet the full text of final aid schemes as approved by the Commission. |
|
(7) |
In the light of changes in transmission of notifications, the provisions concerning the calculation of time limits should be also updated. |
|
(8) |
The methodology for setting the interest rates applicable in respect of the recovery of unlawful aid follows the methodology for setting the reference and discount rates. The methodology for setting the reference and discount rates has been reviewed. The provisions of Commission Regulation (EC) No 794/2004 (4) concerning the interest rate applicable in respect of the recovery of unlawful aid should therefore be amended in order to reflect these changes. |
|
(9) |
In order to enable the Commission to better assess the effects of the notified aid measures on competition in the internal market, questions concerning the potential of such measures to distort competition and to affect intra-Community trade should be included in the notification form. |
|
(10) |
According to the case law of the Court of First Instance of the European Communities (5), when assessing the compatibility of aid with the common market, the Commission must take all the relevant factors into account, including, where relevant, the circumstances already considered in a prior decision and the obligations which that previous decision may have imposed on a Member State. The Commission therefore has power to take into consideration the cumulative effect of any old aid and the new aid, and the fact that the old aid declared unlawful has not been repaid. In order to enable the Commission to apply systematically this case law to individual aid measures as well as to aid schemes, the notification form should be modified. |
|
(11) |
In addition to the changes introduced in Part I of Annex I, further amendments to the notification forms are necessary, in particular the deletion of Part II of Annex I to Regulation (EC) No 794/2004, in order to avoid duplication of the information to be submitted by Member States. |
|
(12) |
Following the adoption by the Commission of new Community guidelines on State aid to promote risk capital investments in small and medium-sized enterprises (6) and the Community framework for State aid for research and development and innovation (7), it is necessary to replace the notification forms contained in Part III.11 and Part III.6(a) and (b) of Annex I, with new notification forms which are in line with the current frameworks. The other notification forms contained in Part III of Annex I remain unchanged. |
|
(13) |
In order to ensure legal certainty and to increase transparency in granting the aid in the Community, the simplified notification form provided for in Article 4(2) of Regulation (EC) No 794/2004 and contained in Annex II should also be amended. In particular, Member States should be required confirm that all commitments given for the purposes of a previously approved scheme will remain valid in their entirety in respect of a new notified aid measure. |
|
(14) |
Regulation (EC) No 794/2004 should therefore be amended accordingly, |
HAS ADOPTED THIS REGULATION:
Article 1
Regulation (EC) No 794/2004 is amended as follows:
|
1. |
Article 3 is replaced by the following: ‘Article 3 Transmission of notifications 1. The notification shall be transmitted to the Commission by means of the electronic validation carried out by the person designated by the Member State. Such validated notification shall be considered as sent by the Permanent Representative. 2. The Commission shall address its correspondence to the Permanent Representative of the Member State concerned, or to any other address designated by that Member State. 3. As from 1 July 2008, notifications shall be transmitted electronically via the web application State Aid Notification Interactive (SANI). All correspondence in connection with a notification shall be transmitted electronically via the secured e-mail system Public Key Infrastructure (PKI). 4. In exceptional circumstances and upon the agreement of the Commission and the Member State concerned, an agreed communication channel other than those referred to in paragraph 3 may be used for submission of a notification or any correspondence in connection with a notification. In the absence of such an agreement, any notification or correspondence in connection with a notification sent to the Commission by a Member State through a communication channel other than those referred to in paragraph 3 shall not be considered as submitted to the Commission. 5. Where the notification or correspondence in connection with a notification contains confidential information, the Member State concerned shall clearly identify such information and give reasons for its classification as confidential. 6. The Member States shall refer to the State aid identification number allocated to an aid scheme by the Commission in each grant of aid to a final beneficiary. The first subparagraph shall not apply to aid granted through fiscal measures.’ |
|
2. |
In Article 8, paragraphs 3 and 4 are replaced by the following: ‘3. With regard to timelimits for action by the Commission, the receipt of the notification or subsequent correspondence in accordance with Article 3(1) and Article 3(3) of this Regulation shall be the relevant event for the purpose of Article 3(1) of Regulation (EEC, Euratom) No 1182/71. 4. With regard to timelimits for action by Member States, the receipt of the relevant notification or correspondence from the Commission in accordance with Article 3(2) of this Regulation shall be the relevant event for the purposes of Article 3(1) of Regulation (EEC, Euratom) No 1182/71.’ |
|
3. |
Article 9 is replaced by the following: ‘Article 9 Method for fixing the interest rate 1. Unless otherwise provided for in a specific decision, the interest rate to be used for recovering State aid granted in breach of Article 88(3) of the Treaty shall be an annual percentage rate which is fixed by the Commission in advance of each calendar year. 2. The interest rate shall be calculated by adding 100 basis points to the one-year money market rate. Where those rates are not available, the three-month money market rate will be used, or in the absence thereof, the yield on State bonds will be used. 3. In the absence of reliable money market or yield on stock bonds or equivalent data or in exceptional circumstances the Commission may, in close co-operation with the Member State(s) concerned, fix a recovery rate on the basis of a different method and on the basis of the information available to it. 4. The recovery rate will be revised once a year. The base rate will be calculated on the basis of the one-year money market recorded in September, October and November of the year in question. The rate thus calculated will apply throughout the following year. 5. In addition, to take account of significant and sudden variations, an update will be made each time the average rate, calculated over the three previous months, deviates more than 15 % from the rate in force. This new rate will enter into force on the first day of the second month following the months used for the calculation.’ |
|
4. |
In Article 11, paragraph 3 is replaced by the following: ‘3. The interest rate referred to in paragraph 1 shall be applied throughout the whole period until the date of recovery. However, if more than one year has elapsed between the date on which the unlawful aid was first put at the disposal of the beneficiary and the date of the recovery of the aid, the interest rate shall be recalculated at yearly intervals, taking as a basis the rate in force at the time of recalculation.’ |
|
5. |
The Annexes are amended in accordance with the Annexes to this Regulation. |
Article 2
This Regulation shall enter into force on the 20th day following its publication in the Official Journal of the European Union.
This Regulation shall be binding in its entirety and directly applicable in all Member States.
Done at Brussels, 30 January 2008.
For the Commission
Neelie KROES
Member of the Commission
Prílohy
ANNEX I
Annex I to Regulation (EC) No 794/2004 is amended as follows:
|
(1) |
Part I. General Information is replaced by the following:
‘PART I GENERAL INFORMATION STATUS OF THE NOTIFICATION Does the information transmitted on this form concern: a notification pursuant to Article 88(3) of the EC Treaty? a possible unlawful aid (1)? If yes, please specify the date of putting into effect of the aid. Please complete this form, as well as the relevant supplementary forms. a non-aid measure which is notified to the Commission for reasons of legal certainty? Please indicate below the reasons why the notifying Member State considers that the measure does not constitute State aid in the meaning of Article 87(1) of the EC Treaty. Please complete the relevant parts of this form and provide all necessary supporting documentation. A measure will not constitute State aid if one of the conditions laid down in Article 87(1) EC Treaty is not fulfilled. Please provide a full assessment of the measure in the light of the following criteria focusing in particular on the criterion which you consider not to be met: — no transfer of public resources (For example, if you consider the measure is not imputable to the State or where you consider that regulatory measures without transfer of public resources will be put in place), — no advantage (For example, where the private market investor principle is respected), — no selectivity/specificity (For example, where the measure is available to all enterprises, in all sectors of the economy and without any territorial limitation and without discretion), — no distortion of competition/no affectation of intra-community trade (For example, where the activity is not of an economic nature or where the economic activity is purely local). 1. Identification of the aid grantor 1.1. Member State concerned: 1.2. Region(s) concerned (if applicable): 1.3. Responsible contact person: Name: Address: Telephone: Fax: E-mail: 1.4. Responsible contact person at the Permanent Representation: Name: Telephone: Fax: E-mail: 1.5. If you wish that a copy of the official correspondence sent by the Commission to the Member State should be forwarded to other national authorities, please indicate here their name and address: Name: Address: … (1) According to Article 1(f) of Council Regulation (EC) No 659/1999 of 22 March 1999 laying down detailed rules for the application of Article 93 of the EC Treaty (OJ L 83, 27.3.1999, p. 1) (hereinafter ‘Procedural Regulation’), unlawful aid shall mean new aid put into effect in contravention of Article 88(3) of the EC-Treaty.
1.6. Indicate Member State reference you wish to be included in the correspondence from the Commission: 1.7. Please indicate the name and the address of the granting authority: 2. Identification of the aid 2.1. Title of the aid (or name of company beneficiary in case of individual aid) 2.2. Brief description of the objective of the aid. Please indicate primary objective and, if applicable, secondary objective(s): Primary objective Secondary objective (2) (please tick one only) Regional development Research and development Innovation Environmental protection Energy saving Rescuing firms in difficulty Restructuring firms in difficulty Closure aid SMEs Employment Training Risk capital Promotion of export and internationalisation Services of general economic interest Sectoral development (3) Social support to individual consumers Compensation of damage caused by natural disasters or exceptional occurrences Execution of an important project of common European interest Remedy for a serious disturbance in the economy Heritage conservation Culture (2) A secondary objective is one for which, in addition to the primary objective, the aid will be exclusively earmarked. For example, a scheme for which the primary objective is research and development may have as a secondary objective small and medium-sized enterprises (SMEs) if the aid is earmarked exclusively for SMEs. The secondary objective may also be sectoral, in the case for example of a research and development scheme in the steel sector. (3) Please specify sector in point 4.2.
2.3. Scheme — Individual aid (4) 2.3.1. Does the notification relate to an aid scheme? yes no — If yes, does the scheme amend an existing aid scheme? yes no — If yes, are the conditions laid down for the simplified notification procedure pursuant to Article 4(2) of the Implementation Regulation (EC) No 794/2004 fulfilled? yes no — If yes, please use and complete the information requested by the simplified notification form (see Annex II). — If no, please continue with this form and specify whether the original scheme which is being amended was notified to the Commission. yes no — If yes, please specify: Aid number: Date of Commission approval (reference of the letter of the Commission (SG(..)D/…): …/…/… Duration of the original scheme: … Please specify which conditions are being amended in relation to the original scheme and why: 2.3.2. Does the notification relate to individual aid? yes no — If yes, please tick the following appropriate box: aid based on a scheme which should be individually notified Reference of the authorised scheme: Title: Aid number: Letter of Commission approval: … individual aid not based on a scheme 2.3.3. Does the notification relate to an individual aid or scheme notified pursuant to an exemption regulation? If yes, please tick the following appropriate box: Commission Regulation (EC) No 70/2001 on the application of Articles 87 and 88 EC Treaty to State aid to small and medium-sized enterprises (5). Please use the supplementary information sheet under part III, 1 Commission Regulation No 68/2001 on the application of Articles 87 and 88 EC Treaty to training aid (6). Please use the supplementary information sheet under part III, 2 (4) According to Article 1(e) of Council Regulation (EC) No 659/1999 of 22 March 1999 laying down detailed rules for the application of Article 93 of the EC Treaty (OJ L 83, 27.3.1999, p. 1), individual aid shall mean aid that is not awarded on the basis of an aid scheme and notifiable award of aid on the basis of a scheme. (5) Commission Regulation (EC) No 70/2001 of 12 January 2001 on the application of Articles 87 and 88 of the EC Treaty to State aid to small and medium sized enterprises, OJ L 10, 13.1.2001, p. 33, as amended by Commission Regulation (EC) No 364/2004 (OJ L 63, 28.2.2004, p. 22), Commission Regulation (EC) No 1857/2006 (OJ L 358, 16.12.2006, p. 3). and Commission Regulation (EC) No 1976/2006(OJ L 368, 23.12.2006, p. 85). (6) Commission Regulation (EC) No 68/2001 of 12 January 2001 on the application of Articles 87 and 88 of the EC Treaty to State aid to training aid (OJ L 10, 13.1.2001, p. 20) as amended by Commission Regulation (EC) No 363/2004 (OJ L 63, 28.2.2004, p. 20) and Commission Regulation (EC) No 1976/2006 (OJ L 368, 23.12.2006, p. 85).
Commission Regulation (EC) No 2204/2002 on the application of Articles 87 and 88 EC Treaty to State aid for employment (7). Please use the supplementary information sheet under part III, 3 Commission Regulation (EC) No 1628/2006 on the application of Articles 87 and 88 of the Treaty to national regional investment aid (8). Commission Regulation (EC) No 1857/2006 on the application of Articles 87 and 88 of the Treaty to State aid to small and medium-sized enterprises active in the production of agricultural products and amending Regulation (EC) No 70/2001 (9) 3. National legal basis 3.1. Please list the national legal basis including the implementing provisions and their respective sources of references: Title: … Reference (where applicable): … 3.2. Please indicate the document(s) enclosed with this notification: A copy of the relevant extracts of the final text(s) of the legal basis (and a web link, if possible) A copy of the relevant extracts of the draft text(s) of the legal basis (and a web link, if existing) 3.3. In case of a final text, does the final text contain a clause whereby the aid granting body can only grant after the Commission has cleared the aid (stand still clause)? yes no 3.4. Access to full text of schemes — in case of an aid scheme please: — undertake to publish the full text of the final aid schemes on the Internet, yes Please provide the Internet address: … — confirm that the scheme will not be applied before the information is published on the Internet, yes 4. Beneficiaries 4.1. Location of the beneficiary(ies): in (an) unassisted region(s): … in (a) region(s) eligible for assistance under Article 87(3)(c) of the EC Treaty(specify at NUTS-level 3 or lower): … in (a) region(s) eligible for assistance under Article 87(3)(a) of the EC Treaty (specify at NUTS-level 2 or lower): … mixed: specify … (7) Commission Regulation (EC) No 2204/2002 of 12 December 2002 on the application of Articles 87 and 88 of the EC Treaty to State aid for employment (OJ L 337, 13.12.2002, p. 3 and OJ L 349, 24.12.2002, p. 126) as amended by Commission Regulation (EC) No 1976/2006 (OJ L 368, 23.12.2006, p. 85). (8) Commission Regulation (EC) No 1628/2006 of 24 October 2006 on the application of Articles 87 and 88 of the Treaty to national regional investment aid (OJ L 302, 1.11.2006, p. 29). (9) Commission Regulation (EC) No 1857/2006 of 15 December 2006 on the application of Articles 87 and 88 of the Treaty to State aid to small and medium-sized enterprises active in the production of agricultural products and amending Regulation (EC) No 70/2001 (OJ L 358, 16.12.2006, p. 3).
4.2. Sector(s) of the beneficiary(ies): Not sector specific Sector specific, please specify according to NACE rev. 2 classification (10): … 4.3. In case of an individual aid: Name of the beneficiary: Type of beneficiary: … SME Number of employees: Annual turnover: Annual balance-sheet: Independence: (please attach a solemn declaration in line with the Commission Recommendation on SME (11) or provide any other evidence to demonstrate the above criteria): … large enterprise firm in difficulties (12) 4.4. In case of an aid scheme: Type of beneficiaries: all firms (large firms and small and medium-sized enterprises) only large enterprises small and medium-sized enterprises (13) medium-sized enterprises small enterprises micro enterprises the following beneficiaries: … Estimated number of beneficiaries: under 10 from 11 to 50 from 51 to 100 from 101 to 500 from 501 to 1 000 over 1 000 (10) NACE is the Statistical Classification of Economic Activities in the European Community. See Regulation (EC) No 1893/2006 of 20 December 2006 establishing the statistical classification of economic activities NACE Revision 2 (OJ L 393, 30.12.2006, p. 1). NACE Revision 2 comes into force on 1 January 2008. (11) Commission Recommendation of 6 May 2003 concerning the definition of micro, small and medium-sized enterprises (OJ L 124, 20.5.2003, p. 36) and Commission Regulation (EC) No 364/2004 amending Regulation (EC) No 70/2001 as regards the extension of its scope to include aid for research and development (OJ L 63, 28.2.2004, p. 22) or any subsequent legislation replacing it. (12) As defined in Community guidelines on State aid for rescuing and restructuring firms in difficulty (OJ C 244, 1.10.2004, p. 2). (13) As defined by Commission Recommendation of 6 May 2003 concerning the definition of micro, small and medium-sized enterprises (OJ L 124, 20.5.2003, p. 36) and Commission Regulation (EC) No 364/2004 amending Regulation (EC) No 70/2001 as regards the extension of its scope to include aid for research and development (OJ L 63, 28.2.2004, p. 22) or any subsequent legislation replacing it.
5. Amount of aid/Annual expenditure (14) In case of an individual aid, indicate the overall amount of each measure concerned: In case of a scheme, indicate the annual amount of the budget planned and the overall amount: For tax measures, please indicate the estimated annual and overall revenue losses due to tax concessions for the period covered by the notification: If the budget is not adopted annually, please specify what period it covers: If the notification concerns changes to an existing scheme, please give the budgetary effects of the notified changes to the scheme: 6. Form of the aid and means of funding Specify the form of the aid made available to the beneficiary (where appropriate, for each measure): Direct grant Reimbursable grant Soft loan (including details of how the loan is secured) Interest subsidy Tax advantage. Please specify: Tax allowance Tax base reduction Tax rate reduction Tax deferment Other: … Reduction of social security contributions Provision of risk capital Other forms of equity intervention. Please specify: … Debt write-off Guarantee (including amongst others information on the loan or other financial transaction covered by the guarantee, the security required and the premium to be paid) Other. Please specify: For each instrument of aid, please give a precise description of its rules and conditions of application, including in particular the rate of award, its tax treatment and whether the aid is accorded automatically once certain objective criteria are fulfilled (if so, please mention the criteria) or whether there is an element of discretion by the awarding authorities. (14) All data should be provided in national currency.
Specify the financing of the aid: if the aid is not financed through the general budget of the State/region/municipality, please explain its way of financing: Through parafiscal charges or taxes affected to a beneficiary, which is not the State. Please provide full details of the charges and the products/activities on which they are levied. Specify in particular whether products imported from other Member States are liable to the charges. Annex a copy of the legal basis for the imposition of the charges: Accumulated reserves Public enterprises Other (please specify): … 7. Duration 7.1. In the case of an individual aid: Indicate the planned date to put into effect the aid If the aid will be granted in tranches, indicate the planned date of each tranche): Specify the duration of the measure for which the aid is granted, if applicable: 7.2. In the case of a scheme: Indicate the planned date from which the aid may be granted: Indicate the planned last date until which aid may be granted: If the duration exceeds six years, please demonstrate that a longer time period is indispensable to achieve the objective(s) of the scheme: 8. Cumulation of different types of aid Can the aid be cumulated with aid received from other local, regional, national or Community schemes to cover the same eligible costs? yes no If so, describe the mechanisms put in place in order to ensure that the cumulation rules are respected: 9. Professional confidentiality Does the notification contain confidential information which should not be disclosed to third parties? yes no If so, please indicate which parts are confidential and explain why: Does the Member State submit a non confidential version of the notification on a voluntary basis? yes no If yes, the Commission may publish this version without further asking the Member State to confirm its content.
10. Compatibility of the aid 10.1. Please identify which of the existing Regulations, frameworks, guidelines and other texts applicable to State aid provide an explicit legal basis for the authorisation of the aid (where appropriate please specify for each measure) and complete the relevant supplementary information sheet(s) in part III: SME aid Notification of an individual aid pursuant to Article 6 of Regulation (EC) No 70/2001, as amended by Regulation (EC) No 364/2004 Notification of an individual aid or an aid scheme pursuant to Article 6a of Regulation (EC) No 70/2001, as amended by Regulation (EC) No 364/2004 Notification for legal certainty Aid for SMEs in the agricultural sector Training aid Notification of an individual aid pursuant to Article 5 of Regulation (EC) No 68/2001, as amended by Regulation (EC) No 363/2004 Notification for legal certainty Employment aid Notification of an individual aid pursuant to Article 9 of Regulation (EC) No 2204/2002 Notification of a scheme pursuant to Article 9 of Regulation (EC) No 2204/2002 Notification for legal certainty Regional aid Notification of aid pursuant to Guidelines on national regional aid for 2007-2013 (15) Notification of aid pursuant to point 64 of Guidelines on national regional aid for 2007-2013 (large investment projects) Notification of aid pursuant to Article 7 of Regulation (EC) No 1628/2006 Notification for legal certainty Research and development and innovation aid Aid for rescuing firms in difficulty Aid for restructuring firms in difficulty Aid for audiovisual production Environmental protection aid Risk capital aid Aid in the agricultural sector Aid in the fisheries sector Aid in the transport sector Shipbuilding aid 10.2. Where the existing Regulations, frameworks, guidelines or other texts applicable to State aid do not provide an explicit basis for the approval of any of the aid covered by this form, please provide a fully reasoned justification as to why the aid could be considered as compatible with the EC Treaty, referring to the applicable exemption clause of the EC Treaty (Article 86(2), Article 87(2)(a) or (b), Article 87(3)(a), (b), (c) or (d)) as well as other specific provisions relating to Agriculture and Transport. (15) Guidelines on national regional aid for 2007-2013 (OJ C 54, 4.3.2006, p. 13).
10.3. Where the existing Regulations, frameworks, guidelines or other texts applicable to State aid do not provide an explicit basis for the approval and in so far that it is not requested by the relevant supplementary information sheet(s) in part III, please provide the following information concerning the likely impact of the notified measure on competition and trade between Member States. This information is necessary to complete the assessment made by the Commission which balances the positive impact of the aid measure (reaching an objective of common interest) against its potentially negative side effects (distortions of trade and competition). 10.3.1. For individual aid: (A) Impact on competition: Please specify and describe the product markets on which the aid is likely to have a significant impact, the structure and dynamics of those markets and the indicative market share of the beneficiary: (B) Impact on trade between Member States. Please provide information on the effects on trade (shift of trade flows and location of economic activity): 10.3.2. For aid schemes: (A) Impact on competition: Please specify and describe the product markets on which the aid scheme is likely to have a significant impact, the structure and dynamics of those markets: (B) Impact on trade between Member States. Please provide information on the effects on trade (shift of trade flows and location of economic activity): 11. Outstanding recovery orders 11.1. In the case of individual aid: The authorities of the Member State commit to suspend the payment of the notified aid if the beneficiary still has at its disposal an earlier unlawful aid that was declared incompatible by a Commission Decision (either concerning an individual aid or an aid scheme), until that beneficiary has reimbursed or paid into a blocked account the total amount of unlawful and incompatible aid and the corresponding recovery interest. yes no 11.2. In the case of aid schemes: The authorities of the Member State commit to suspend the payment of any aid under the notified aid scheme to any undertaking that has benefited from earlier unlawful aid declared incompatible by a Commission Decision, until that undertaking has reimbursed or paid into a blocked account the total amount of unlawful and incompatible aid and the corresponding recovery interest. yes no 12. Other information Please indicate here any other information you consider relevant to the assessment of the measure(s) concerned under State aid rules. 13. Attachments Please list here all documents which are attached to the notification and provide paper copies or direct Internet links to the documents concerned. 14. Declaration I certify that to the best of my knowledge the information provided on this form, its annexes and its attachments is accurate and complete. Date and place of signature: Signature: Name and position of person signing: ’ |
|
(2) |
Part II is deleted; |
|
(3) |
Part III is amended as follows:
|
ANNEX II
Annex II to Regulation (EC) No 794/2004 is replaced by the following:
‘ANNEX II
SIMPLIFIED NOTIFICATION FORM
This form may be used for the simplified notification pursuant to Article 4(2) of Commission Regulation (EC) No 794/2004 implementing Council Regulation (EC) No 659/1999 laying down detailed rules for the application of Article 93 of the EC Treaty (1).
1. Prior approved aid scheme (2).
1.1. Aid number allocated by the Commission:
1.2. Title:
1.3. Date of approval [by reference to the letter of the Commission SG(..)D/…]:
1.4. Publication in the Official Journal of the European Union:
1.5. Primary objective (please specify one):
1.6. Legal basis:
1.7. Overall budget:
1.8. Duration: …
2. Instrument subject to notification
New budget (please specify the overall as well as the annual budget in the respective national currency): …
New duration (please specify the starting date from which the aid may be granted and the last date until which the aid may be granted): …
Tightening of criteria (please indicate if the amendment concerns a reduction of aid intensity or eligible expenses and specify details): …
3. Validity of commitments
Please confirm that the commitments provided by the Member State for the purposes of the prior approved aid scheme are valid in their entirety also for the new notified measure.
Please attach a copy (or a web link) of the relevant extracts of the final text(s) of the legal basis.
(1) Commission Regulation (EC) No 794/2004 of 21 April 2004 implementing Council Regulation (EC) No 659/1999 laying down detailed rules for the application of Article 93 of the EC Treaty (OJ L 140, 20.4.2004, p. 1). Regulation as last amended by Regulation No 1935/2006 (OJ L 407, 30.12.2006, p. 1).
(2) If the aid scheme has been notified to the Commission on more than one occasion, please provide details for the latest complete notification that has been approved by the Commission.’
Poznámky
(1) OJ L 83, 27.3.1999, p. 1. Regulation as last amended by Council Regulation (EC) No 1791/2006 (OJ L 363, 20.12.2006, p. 1).
(2) Details on the established web application are published in Commission notice ‘D including addresses together with the arrangements for the protection of confidential information’ (OJ C 237, 27.9.2005, p. 3).
(3) Details are published in Commission notice ‘D including addresses together with the arrangements for the protection of confidential information’.
(4) OJ L 140, 30.4.2004, p. 1. Regulation as last amended by Regulation (EC) No 1935/2006 (OJ L 407, 30.12.2006, p. 1, as corrected by OJ L 44, 15.2.2007, p. 3.)
(5) Joined cases T-244/93 and T-486/93 TWD Textilwerke Deggendorf GmbH v Commission of the European Communities, [1995] ECR II-2265.